First Work Team Leaves Puerto Maldonado



After 8 days of hard work, we had completed the second story walls, roof, and 3 sides of the outside security wall. We dug 7 footings for columns, formed 150 feet of foundation wall, tied rebar for 300 feet of beams and 7 columns, carried and installed over 4000 concrete blocks, used 120 bags of cement and hauled an estimated 1,080 buckets of concrete, built 4 roof trusses, installed 120 sheets of metal roofing, and roughed in the main electrical panel and 25 electrical outlets. Many great friendships were formed between both the American team members and the Peruvian team members. Praise God for these men and their willingness to come use their construction skills here in Peru.